Preconstruction Review
Preconstruction Review (RA):
A Preconstruction Review, consisting of a combination of a Construction Documents Review and a Construction Cost Review, performed by BCI includes the following:
Review the following documents which BCI can assist in collecting:
Information from the Lender relating to the budget.
- The loan budget including:
- total loan amount
- amount of loan allocated to direct construction costs
- contingency amount and how contingency is allocated (soft or hard or both?)
- Funding sources and any timing requirements for release of funding sources:
- equity contribution requirement amount if any and when?
- participation with other lenders
- trigger for commencement of release of Lender’s funds
- Loan timing requirements including:
- the construction loan maturity date
- extension options available?
- how long/how many?
- construction commencement date
- substantial completion date
- The Lender’s funding parameters during construction including:
- retention % and release requirements
- payment allowed for stored materials? What documentation is required?
- change order parameters if any (i.e. maximum aggregate amount, maximum individual amount) or the borrower is responsible for payment of all change orders
Information from the borrower and/or relating to the proposed project:
- Signed and sealed final plans and specifications including:
- site (grading, water and sewer, roads, storm water management)
- architectural
- structural
- mechanical and electrical
- tenant improvement drawings where applicable
- The plat, preferably recorded, and/or other survey documentation indicating:
- all site boundaries, easements, building restrictions, rights-of-way and buffer zones
- evidence the property is zoned for the intended use
delineated flood plain and wetlands
- Engineering reports including information on:
- geotechnical conditions, subsurface and soil conditions with the engineer’s earthwork and foundation design recommendations
- environmental report, if not performed by BCI, including historic and current site conditions, Freedom of Information documentation and environmentalists recommendations for further action
- condition survey report, if not performed by BCI, describing the existing major building systems for improvements to remain where applicable
- Documentation relating to the construction contracts and agreements, including:
- fully executed copy of the owner/architect agreement
- fully executed copy of the general construction contract or construction management agreement with all attachments and exhibits, addenda or executed change orders
- contractor’s breakdown of all direct construction costs/schedule of values
- proposed construction schedule
- Documentation indicating necessary public or utilities approvals are in place, including:
- copies of grading, building and other special permits or any required variances or proffers required by local, state or federal regulations
- verification of availability of utilities, including water, sanitary sewer, gas, electric, telephone
- fully executed copies of any public works agreements for on- or off-site work
Limited Preconstruction Review (RB):
A Limited Preconstruction Review, which combines a limited Construction Documents Review and a Construction Cost Review, conducted by BCI includes the following:
Review the following documents, which BCI can assist in collecting:
Information from the Lender relating to the budget
- The loan budget including
- Total loan amount
- Amount of loan allocated to direct construction costs
- Contingency amount and how contingency is allocated (soft or hard or both)
- Loan timing requirements including
- Construction commencement date
- Substantial completion date
- The Lender’s funding parameters during construction including
- Retention % and release requirements
- Payment allowed for stored materials? What documentation is required?
- Change order parameters if any (i.e. maximum aggregate amount, maximum individual amount) or the borrower is responsible for payment of all change orders
Information from the borrower and/or relating to the proposed project:
- Signed and sealed final plans and specifications including:
- site (grading, water and sewer, roads, storm water management)
- architectural
- structural
- mechanical and electrical
- Documentation relating to the construction contracts and agreements, including
- fully executed copy of the general construction contract or construction management agreement with all attachments and exhibits, addenda or executed change orders
- contractor’s breakdown of all direct construction costs/schedule of values
Cost Review (RC):
BCI can provide the following Cost Review services:
- Review the following documents:
- Plans and specifications
- Contractor’s cost breakdown for the project; the client will provide copies of the cost breakdowns from the contractor
Review costs for the construction/rehabilitation of the project and compare to the contractor’s proposed cost breakdown
- Prepare a brief letter-type report for the project including:
- A brief description of the proposed improvements
- An evaluation of the contractor’s proposed improvements’ costs
- A summary of the project
- An attachment listing the documents reviewed